JW Aluminum began by building a current-state model in Simul8. The goal was to recreate how the plant was performing, including the hours required on key resources and the amount of finished material leaving the facility.
The team progressively added real-world constraints and compared the model with actual operations. When differences appeared, JW Aluminum worked with Simul8 to identify what was missing and represent those conditions more accurately. The model came to closely replicate plant performance, giving the team a reliable environment for testing potential changes.
JW Aluminum then presented the current-state model to the management team, and plant leaders were encouraged to challenge the model and identify anything that didn’t look right. The team refined it based on their feedback before moving to future-state scenarios, building confidence in both the model and the decisions it could support.
The validated model was used to test routing, scheduling, upstream material, and quality refinements.
JW Aluminum modeled three routing changes and one quality-related change, giving teams a common fact base to compare options and agree on impactful next steps.
Simul8 also helped quantify ideas that had previously been supported mainly by operational experience. In one example, the team evaluated whether certain products should continue moving between two mills for flexibility or be routed through one higher-powered mill to reduce the number of rolling passes. The model showed where consolidating routes could deliver a meaningful productivity benefit.
The team also modeled the effect of reducing the thickness of material arriving from an upstream process. JW Aluminum had identified and discussed the possible change before, but quantifying its impact helped the broader organization understand its importance and raise its priority.
One of the clearest insights involved the annealing ovens. Each oven could hold six coils, so the original model assumed full six-coil loads. When the results did not match actual production, the team reviewed the operating data and found that ovens often received only four or five coils, with an average closer to five. Upstream rolling could not always provide six compatible coils quickly enough to keep every oven full.
Once that constraint was added, the simulation came close to the plant’s actual production rate.
This finding helped JW Aluminum focus on improving upstream flow and equipment availability so the ovens could be loaded more consistently and efficiently.
More consistent loading could help optimize oven utilization, support dependable scheduling, and further support reliable delivery to customers.